Darwin System
Erection Instructions
Step 1
• |
Set the base jacks. |
• |
Mark the location of base jacks (or U-Head Jack) |
• |
Put base jacks on marked position and adjust height to the right length as the drawing. |
Step 2
• |
Install the vertical and horizontal. |
• |
Level check. |
• |
Level and vertical structure. |
Step 3
• |
Install the Cross Handrail and Horizontal. |
Step 4
• |
Install the Catwalk and Staircase. |
Step 5
• |
Install the Aluminum Stair Frame. |
• |
Install the Toe Board. |
Step 6
• |
Install the Stair Corner Guard. |